The isometric shows the drainage piping of a two-story dwelling. No cleanout is shown anywhere. Under the IPC, at which of the labelled points is a cleanout required?
- A. A — where the building drain changes horizontal direction 90 degreesCorrect answer
- B. B — where the building drain makes a 22.5-degree horizontal offset
- C. C — where the building drain drops to a lower elevation
- D. D — where the vertical soil stack turns into the horizontal building drain
Why
IPC 708.1.4 requires a cleanout where a horizontal drainage pipe, building drain or building sewer changes horizontal direction more than 45 degrees (45 degrees or less is permitted without one). Point A is that fitting: the building drain turns 90 degrees in plan, so the cleanout belongs there. Point B is only a 22.5-degree offset in plan — not more than 45 degrees, so 708.1.4 adds nothing. Point C changes the elevation of the drain, not its horizontal direction: the pipe keeps running the same way in plan. Point D is the turn from the vertical soil stack into the horizontal building drain — again not a change of horizontal direction, and the same is true of any other vertical-to-horizontal turn. The interval rule of IPC 708.1.1 does not require a cleanout here either: the whole run shown is far shorter than the 100-foot interval it sets, and the 708.1.3 cleanout at the junction of the building drain and the building sewer is not on this sheet (the sewer leaves the drawing).